on 06-26-2008 10:31 AM
HI Experts,
I am creating a service order automatically froma repair order (sales document), the service order is relaese automativally at the time of creation, this was working perfectly fine but now it is not working, i am not able to figure out what could be the reason why it is not releaseing automativally now.
Pls help - Urgent.
Rgds
Hi to all experts out there!
Further to the problem outlined w.r.t. permits, I have the following issue:
1. PM order status: CRTD (not released yet)
2. Perform planning to accumulate cost within the 1st (or higher) level of permit to be issued.
3. If the user saves the order before release, the system will not allow release before issuing of permit afterwards - INTENTIONAL.
4. However, the system does allow RELEASE of PM order (directly after planning) and then save BEFORE issuing of permit - LOOP HOLE.
In SAP standard I am unable to find a config setting to prevent the situation in point 4.
Any suggestions to resolve the above issue?
Have a great weekend!
Lew.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Cehck the service ordertype configuration.
SPRO --> PM/CS --> Maintenance processing --> Orders --> Maintenance ordertypes. Check the relevent order type, bottom of the screen you can find a check box Release automatically. If you check it, it will release the order automatically.
Prase
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.