What all needs to be tested to ensure PS module is fine in SAP migrated system.
Please list a few tasks.
Thanks & Regards,
Hi Please ensure the following things:-
1. Total qty of PD have been uploaded.
2. Total qty of WBS Have been uploaded.
3. Total qty of Network have been uploaded.
4. Total Qty of Activities have been uploaded.
5. Total Plan cost line item have been upload and also check the amount Cost element wise. Ensure that all these cost elements have been maintaine Line item for RA.
6.Total Planned revenue have been uploaded also check Revenue element wise. Planned revenue should reflect with negative sign.
7.Total Commitments are correct.
8. Budget Values are correct.
9. Total actual cost line items have been uploaded. Check the amount cost element wise.
10. Total Actual Revenue have been uploaded. Check the value in revenue element report.
11. All project WIP have been uploaded.
Regards
Rahul Tyagi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.