Hi all,

in a very early stage of my project I plan costs using CJ40. I have also plan payments using CJ48. Is there any SAP standard functionality that transfers the values planned in CJ40 into CJ48? I suppose there isnot, but could You confirm this?

Thanks a lot.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

I suppose the plan costs thru CJ40 are not linked to payments in CJ48 because cost in CJ40 would be for your your internal use, I mean this is the cost of the material which u r going to use in your project, and cost in CJ48 will be payments that will be made to vendors or contractors . .. I guess.

So even if there is some possibility in SAP to transfer the plan cost of CJ40 into CJ48 ( As i have not heard of that thing yet ) , Even then i think , it will be of no use.

May this will clear the doubt.