on 06-25-2008 8:00 AM
Hi Friends,
We want to integrate the PS module with PM module.
We have to link equipment no of PM to WBS element of PS.
Will it be possible ? If yes please suggest the procedure.
Regards,
Pradip
Hi,
You can integrate PM with PS.
You can assign WBS element in equipment master in Organisation Tab.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
WBS is a cost collecting object (account assigned) and you can link WBS and equipment by entering WBS element in the master data of equipment under organisation tab.
When creating a PM order with configuration you can transfer WBS information on the equipment to the order. And this order now can then be checked for during availability control.
Refer below link for response to similar post.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.