I have a problem when exported my roadmap to MS Project, if assign dates on data plan this is not exported, only those task that have dates on actual data are exported.

if someone knows how to solve this problem I would appreciate your information.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi ,

refer to the note 799709, you might get an idea.

Former Member
0 Kudos

hi i think i have narrowed down your problem

to the note 1041576 , you need to implement this note.

regards ,

varghese

Former Member
0 Kudos

hi, could you just let me know whether your problem is solved or not ,if not i can still help you regarding this if you can give me specific details

regards,

Varghese

Former Member
0 Kudos

Hi,

Sorry for not having responded sooner.

We have implemented the notes that you refer but my problem still continue, if you have more information about how to solve this problem i apreciate it in advance.

Former Member
0 Kudos

HI,

I resolved the problem, i didn't applied the note that you refer correctly.

Thank´s for your help it was very helpful.

Former Member
0 Kudos

hi veronica,

Can u explain me about wat you did for resloving that problem, may be it will be helpfull for me also.

and by the way if you are maintaing the project management details in RMMAIN tcode then can you give me some more information regarding this.