SD material price change should refresh Delivery order.

sanjaypetkar
Explorer
0 Kudos

There was a price change for the material after creation of outbound delivery. a dynamic credit limit management is enabled which blocks the creation of delivery order if there is no sufficient credit available for party. Now after change in prices the delivery order should go to credit block while doing PGI. which is not happeining. At Billing creation the prices gets refreshed and party is billed with new rate. This is creating debit balance in customer account. Kindly suggest solution how to block the PGI in such cases?

Regards

Sanjay Petkar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Please check the VOV8 credit group filed configuration. If it is 2 at delivery level. Then only it do credit check at delivery level...

Regards

sankar