what comprises total committed costs?

Former Member
0 Kudos

hi to all,

i made PR, PO, MIGO and MIRO and during each step i checked report (CN41) but total cost commitment remained 0 all throughout..

i would like to ask whether what causes a committed cost? and what configuration/customization do i need to undertake in order to make the correct settings?

thank you..

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

T Code OKKP, activate the component 'Commitments Management' to '1-Components Active'.

Then use T Code SE38 and execute the program RKANBU01 mentioning the WBS to which PR/PO are assigned.

Now you should be seeing the commitments in reports

Regards

Sreenivas

Answers (1)

Answers (1)

Former Member
0 Kudos

hi..

thanks for the answer.. i carried out the steps you mentioned but still no output for committed costs.. perhaps there might be something else i'm missing?

thanks in advance.

varshal_kachole3
Active Contributor
0 Kudos

Hi,

1. Tcode FS00.

2. Edit cost element Tcode KAH2. Enter cost element category 90.

3. Mention this Cost element in the OBYC in BSX for the desired valuation class.