on 06-24-2008 8:52 AM
hi to all,
i made PR, PO, MIGO and MIRO and during each step i checked report (CN41) but total cost commitment remained 0 all throughout..
i would like to ask whether what causes a committed cost? and what configuration/customization do i need to undertake in order to make the correct settings?
thank you..
T Code OKKP, activate the component 'Commitments Management' to '1-Components Active'.
Then use T Code SE38 and execute the program RKANBU01 mentioning the WBS to which PR/PO are assigned.
Now you should be seeing the commitments in reports
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi..
thanks for the answer.. i carried out the steps you mentioned but still no output for committed costs.. perhaps there might be something else i'm missing?
thanks in advance.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.