on 06-23-2008 10:55 AM
I am in SCM 4.1 and I defined a product interchangeability in the transaction /INCMD/UI.
Sould I define this product substitution also in SAP R/3 ?
In the substitution, I defined product A substituted by product B. I have a planned order where I have the product A. When I convert this planned order to production order, normally if I understood well the system should replace automatically the product A by the product B and it is not the case. I have an error in the CIF "Screen output without connection to user".
Can someone help me ?
Thank you in advance.
Isabelle Eustache.
Hi,
Firstly you have to define this product substituion in ECC.
Secondly would like to understand that how did you get a Planned Order of A from APO when you have defined the Interchangeability in APO. You should have got a planned order of Product B instead of Product A.
Regards,
Tushar Bhalla.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello ,
Thank you for your answer.
Please could you tell me what you mean by ECC.
And in APO, when I define A is substituted by B, I have substituted orders on A and dependant needs on B correspond with substituted orders of A.
And my problem is when I want to convert a planned order where I have the component A, I have an error in the CIF.
Regards.
Isabelle Eustache.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.