on 06-23-2008 6:07 AM
Hello Guys
What is the significances of TOR & Availability Check in normal manufacturing Scenario. What are the configuration steps need to be done.
Thanks
Vj
Hi,
we do TOR and availability check when we want to plan requirements and confirm a date to the customer when the stock can be made available. The concept applies the same way to a manufacturing or any other whcih wants to utilize the functionality.
regards
sadhu kishore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please go through this link.
[Availability and TOR|http://help.sap.com/saphelp_erp60_sp/helpdata/en/93/744b51546011d1a7020000e829fd11/content.htm]
[Availability and TOR|http://help.sap.com/saphelp_46c/helpdata/en/17/fdeb47b535d1118b3f0060b03ca329/content.htm]
Thanks,
Vrajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.