Hi All,
My requirement is that my client wants to settle costs/Revenunes partially.
So which Settlement rule i need to create-PER or FUL.
Also in CJ88 which processing type i should select-Automatic,By period or Full settlement.
Pls advice.
muzamil
User Per in settlement rule and after completion of project then u can go for Full settlement.
Normally for Investment Projects, at the time of AuC settlement to FX Asset Full carryout...(i.e. CJIC)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Select Automatic and give Periodic. Mention the desired %.
Full will settle all the values (100%). This has to be done at the end of the project, when TECO is set.
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.