HI Guru
In Mat master inspectiontype13 is active,In recepie for material and version ,Inspection charac.assigned in Operational level,Inspection point is quantity based
After releasing the Process order,Inspection lot not generated
I try to create through transaction MFPR, Inspection lot not created
Where I missed ,first time i am in REM industry
(If I assigned inspection type 04, inspection lot is generated-- early insp. lot assigned in mat.master)
Please guide me in detail...
How to create inspection type 13,what are the steps to be folllowed ?
please correct me
thanks
Hi,
Follow the below mentioned steps -
1. In the material master record for the finished product, you must set the indicator for quality inspection in the Quality Management view. Moreover, in the QM inspection data, you must also select and activate an inspection type with the origin 13 (repetitive manufacturing).
2. You must select a repetitive manufacturing profile in the material master record of the finished product.
3. You must create a production version and a product cost collector.
4. In the routing for the finished product, you must maintain characteristics for the operation for which inspection results are to be created.
Let me know if you still have issue.
Sanjay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.