Sales Pricing...Problem ........

Former Member
0 Kudos

Good Morning Experts.........

I am doing sales pricing after Easy cost planning from Project Builder ..........I find a error "NO ORDERING PARTY Exist in project PS.001"......The details of error is given below---

No ordering party exists in project PS.0009

Message no. VPK1121

Diagnosis

The system cannot carry out sales pricing for one of the following reasons:

No partner is defined for the sold-to party partner role in the project.

The sold-to party has not been created in the sales area specified for the sales pricing.

System response

Sales pricing is not possible.

Procedure

Go to the project definition and maintain a partner for the sold-to party/> partner role.

If necessary, you must also create the partner in the sales area specified in the project definition for the sales pricing.

I have defined Partner Determinatin procedure in Project System and calld that in Project defintion ...

Please clear me ...where is the problem ........

A good Explanation will be rewarded with good marks

Thanks in advance

Regards

SMITH

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

ans

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Step1: Maintain the DIP Profile (specifically customized for the Easy cost planning) in control data sales pricing tab of the project definition.

Also mention the Sales organization, distribution channel, division.

Step2: Mention the "PartnerDetermProced." in the same tab below simulation profile. (this is maintained in Tcode OPSPAR3 partner function procedure as SP Sold to party)

Step3. After this check that the partner tab has appeared in the Project definition.

Step4: Mention the function as Sold to party.

Partner as the Customer Tcode XD01(Get help of the SD Consultant for this) .

The error will go away.

Thanks..

Former Member
0 Kudos

Can anyone solve this problem .......or NOT......

Regards

SMITH