Dear experts,
There is a billing plan in the WBS, but I don't konw how to use it. I want to create billing for this WBS, I don't know is it possible to create billing document from this billing plan directly?
thanks
Lance
Hi,
This billing paln is generally created for revenue planning during early stages of Project when sales order doesnt exist. You can copy this billing plan to Sales order. Refer [Billing Plan|http://help.sap.com/saphelp_erp60_sp/helpdata/en/4c/22744246e611d189470000e829fbbd/frameset.htm]
Billing will happen when block in billing plan of Sales order is removed. In case of milestone billing, when you confirm a milestone, billing block is removed and you can proceed to Billing.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi lance,
billing plan in WBS is for information nd is not operative you need to maintain separate billing plan in sales order nd carry out ur billing process.
regrds
pushpa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.