on 06-19-2008 4:39 AM
Hi,
I have an activity named "Activity1":
Start date = ST = 01/01/2008
End date = ST + 10
work = 120H
duration = 10day
Activity type = Labor
I want to assign workers into the activity as follows:
01/01/2008: 10H
02/01/2008: 20H
03/01/2008: 30H
04/01/2008: 40H
04/01/2008 - 10/01/2008: 12H
can Sap support this?
Please help!
Thanks
Hello Long Nguyen,
The Project Manager can use following T.code to view Workforce planning.
(1) CMP2 --> Project View (It would list the workforce planing for the particular project/s)
(2) CMP3 --> Work Center View.(It would list the workforce planing for the particular workcenter/s)
(3) CMP9 --> Evaluation (Workforce Planning Reporting)
Thanks & Regards,
Anish Walinjkar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
1. Tcode OPB2, Maintain the Function name as required.
In fucntion definition Maintain as below:
% Duration % Req.
0 9%
10 18%
30 27%
40 36%
50 10%
2. Maintain the distrubution Strategy in:
SPRO-->PS->Resources->Distrubution->Define distribution strategy.
3. Mainain Req. distribution in:
SPRO-->PS->Resources->Distrubution->Define requirement distribution.
4. Maintain this distribution key on the Internal activity in "DistKeyCapRqInt" in internal tab below the control key.
If needed please take help of PP Consultant as well.
hope its useful.
thanks..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.