Dear All
I have assigned the latest roadmap to my project.
Now the detailed phases in ASAP are displayed.
When I click on it, it takes me to a screen, where lot of activities are displayed.
Is it mandatory to assign documents for every step.
If yes or no, how to create my logo to the documents.
Reg
Suresh
Hi Suresh,
Adding on to previous reply.
The navigation structure of roadmap consists of
Phases
(ii) Work Packages
(iii) Activities
(iv) Tasks
It is not mandatory to use the roadmap and create documents for eac activity/tasks. You may just refer to the accelartors provided for the task and activities while executing them.
Following features are available in roadmap for project specific use.
Status & Notes
(ii) Upload Project Documents
(iii) Create messages
(iv) Limited reporting capabilities
It is purely your(PM's) decision to use a roadmap or not for project. If you need I can guide you in detail on the use of abovr 4 project specific features of roadmap. Let me know that and pls assign points.
Rgds
Manish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Suresh,
To begin with, Usage of Roadmap transaction (RMMAIN) is not mandatory.
It is of course helpful, if your project does work as per the Roadmap.
As regards documentation templates, please go to SOLAR_PROJECT_ADMIN, to Project Standards tab and you can create any custom document types with your specific template.
Best regards,
Srini
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
13 | |
13 | |
11 | |
11 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.