Hello everyone,
I am using milestone billing for my project with network milestone dates linked to my sales order billing plan. Due to some wierd reasons, i am not able to see my revenue, both planned and actual on the CN41 revenue reports. Could anyone advise if I am missing some customization?
Thanks,
Nithin
In planning profile (OPSB), is the check box under section 'Automatic revenue planning' at the bottom ticked. Tick 'From sales order'. Also check if 'Revenue CE grp.' is maintained.