Dear All,
Kindly let me know how to link purchase order with WBS element. My query is that, client has make Rs.1000 as an approved budget. but while making PO against WBS element, system is allowing to create PO for more than Rs.1000 also.
Kindly let me know how to solve the problem along with t code n customisation. Since i m mm cons , i m not much aware about Project system, wbs element etc.
Reward is for sure for imm reply..
regards,
Please check whether Project Stock Valuation Class is mentioned in the Material Master Accounting 1 view screen or not? If not maintain the Project Stock Valuation Class in the Material Master.
Regards,
Praveen.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
1. Maintain Budget Profile OPS9
Maintain the tolerance limit for this Budget profile for "++" transaction group
2.Maintain this budget profile in OPSA.
3. CJ30. assigne the budget
4 .CJ32 release the budget.
5. Tcode: CJBN
6. Tcode: CJBV.
Now try to create PO.
thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
9 | |
9 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.