on 06-18-2008 12:04 AM
Hello,
We have a situation where we are transferring goods between plants (same company code) using an STO of type UB to delivery type NL. Right now each PO gets its own delivery document, but we would like to run the delivery due list and consolidate the PO's onto one delivery. Can someone point me in the right direction? I haven't been able to find any PO to DL copy control.
thanks in advance
You can try maintaining order combination requirement in customer master.
If you see the PO document, there is a field for ORDER COMBINATION. Only if that is ticked, I think the system shall allow combining the POs into a single Delivery document.
Please let us know if it helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.