Hello,

executing the evaluation "Cost/Revenue Costing for Project" I get no results. Could someone tell me where the values for this report come from? Can I find somewhere a list with all the evaluations (except the one like completed checkpoint items, ... which are really self explaining) and the source of the shown values?

Thx, Max

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

I hope that you have assigned Cost revenue rate to Roles.

Check in spro> cProjects> Evaluation--> Define extract layout, Iterator for the specific layout RES_PART, Object and attributes.

Also check in Define evaluation assigned extract layout to Evaluation is correct which is defined in earlier step.

Regards,

Karan Hon

Award if useful..

Konstantin
Participant
0 Kudos

Hi Max,

All evaluations (and it's sources) you can find here: SAP IMG -> Collaboration Projects -> Evaluations.