on 06-16-2008 11:37 AM
Can anyone advice the following statement from SAP documents? This is pertaining to milestone billing.
During partial invoicing, the amount of the down payment to be cleared can be changed (by changing the amount for condition type AZWR on the pricing screen for the item).
While doing the partial invoicing 'F2' after the inital downpayment request 'FAZ', i did not see condition 'AZWR' being proposed for me to make changes. Is there something i missing? Is the proportional settlement of downpayment done in SD billing?
Thanks
Peter
Did you maintain for your contract - billing date & down payment amounts in your billing plan.
If yes, system would propose AZWR condition and you could change it as per your requirement
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
'AZWR' is there in the procedure. When i tried to add condition manually in F2 document, it's appearing as '0' and non-editable. Pls correct if i hv wrong understanding regarding this functionality while creating partial invoice.
Thanks
Peter
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Just make sure you configure the condition type AZWR in your pricing procedure, to let you change the downpayment during partial invoicing.
Regards,
Siddharth.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.