standard value key used in PS workcenter

Former Member
0 Kudos

Hi PS gurus,

Can any body explain me following steps to create ,

a) work center for my activity -i)which should be my work center category? .ii) standard value key for the same.

Regrds

J kumar

Accepted Solutions (1)

Accepted Solutions (1)

varshal_kachole3
Active Contributor
0 Kudos

Hi,

1. Go to Tcode: CNR1, mention the plant for which you want to create the Work center Give some name to work centre (e.g Design, Purch) Work center category 006.

2. Go to capacities tab enter capacity category (eg. Labour)

Other formula select the relevent (e.g SAP008)

Inside the capacity enter the calender ID, base unit of measure as HR. mention the start and finish time for the work center,

give break duration (e.g 1 hr, 30 min ) capcpity utilization 100%

Mentione the number of the capacities as the number of the head count in that work center..

3. Go to scheduling tab enter other formula (e.g SAP004)

4. Go to costing tab mentione the validity dates for the work center start with e.g 01.01.2008.. select appropriate cost center. in the area next to activity types mentioen the formula e.g SAP008.

5. Go to T.code KP26 maintain the hourly rates for the cost center and activity types combination.

6. Goto T.code CJ20n, select the activity enter the work center in the Internal Tab and mention the work duration in hours..

Hope its useful.

Thanks.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Kumar,

Please check the previous threads for your clear cut information.

( I can't copy and paste due to authorisations)

I hope that helps you most.