on 06-14-2008 4:15 PM
Hi friends,
My project report S_ALR_87013558 shows negative value
in available amount.But the system has not triged any error message even though the i have set 100% usage action 3 in tol group
My assumption is that the value is being consumed by rem ord plan value.
My client want to drill down the Rem ord plan value
can any body tell how to do this.
is there any standard t code to drill down the rem ord value
so that i can trace out the inconsitences in the report
Points rewarded for suggestion
waiting for a speedy reply since i am in a crisis situvation
Regards
pv
Edited by: pv on Jun 14, 2008 5:16 PM
Hi pv,
check the following :
In which currency you are viewing the report S_ALR_87013558
1.controlling area currency
2.Object currency.
In Cj20N check the change document status when
budget avaliability control has been activated.
check whether any commitments is there before
or after AVAC and see any PM orders are assign the WBSE.
SAP note for residual order plan-- 21649,922177
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.