on 06-13-2008 3:53 PM
Dear All,
How to attach a quality plan automatically so that inspection lot gets the system status as REL CALC without maintaining the relation between material & quality plan. This situation arises when lakhs of materials are created through interface programs in to SAP with activation of inspection types and all are having one common plan.
Thanking you
Venkat
Hi,
You need to assign material to inspection plan as you are telling you have lakhs of material , please develope a LSMW or BDC program to assign the material to inspection plan.
Sanjay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can't. The material must be assigned in QP02 to the plan.
Craig
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.