Dear Experts !
I want to lock Cost Planning for a perticular period ...for this i am doing setting in OKP1 with controlling area wise ...But this is not working ....
Please Clear me where I am wrong.
Regards
SMITH
ans
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
OKP1 locks the plan data for the controlling area, fiscal year, Version and business transaction combinations.
If you want to lock the planning for the particular WBS, you can do the same in Project Builder under the menu path Edit-> Status-> Lock -> Planning.
Just see this serves your purpose.
Regards
Ramesh