V_V2 with date selection

Former Member
0 Kudos

Hi gurus,

transaction V_V2 Reschedulling sales order hasn't date selection criteria. Is not posible only reschedulling a group of sales order by date selection???

Thank you!!!

I will reward points all answers!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Backward and Forward Scheduling

Backward scheduling is the calculation of deadline dates: the arrival time at the customer site is calculated as the earliest possible goods receipt time at the customers unloading point on the requested delivery date. All four of the delivery and transportation scheduling lead times are subtracted from the customer's requested delivery date to determine if this date can be met.

The transit time, loading time, and pick/pack time are subtracted from the customeru2019s requested delivery date to calculate the required material availability date.

The system calculates backward scheduling as follows:

Requested delivery date minus transit time = Goods issue date

Goods issue date minus loading time = Loading date

Loading date minus transportation lead time = Transportation scheduling date

Loading date minus pick/pack time = Material availability date

By default, the system will calculate delivery dates the closest day, taking into consideration the working days of the shipping point and a rounding profile. In this case the system assumes a 24 hour work day and lead times can be entered in days up to 2 decimal points. This is referred to as daily scheduling.

Precise scheduling calculated down to the day, hour and minute is supported. This allows the scheduling of a delivery within a single day. It is activated by maintaining the working hours for a particular shipping point.

Backward scheduling is always carried out first. If the material availability date or transportation scheduling date is calculated to be in the past, the system must then use forward scheduling.

Forward scheduling is also done if no product is available on the material availability date calculated by backward scheduling. The system does an availability check to determine the first possible date when product will be available. This new material availability date forms the starting point for scheduling the remaining activities. The loading time, pick/pack time, transit time, and transportation lead time are added to the new material availability date to calculate the confirmed delivery date.

Reward if useful.

Regards,

Anbu

Former Member
0 Kudos

Any idea more?

Former Member
0 Kudos

Hi,

You can try with other program : SDV03V01

But, if you want to keep functionnalité of V_V2, you can create new program in copy of SDV03V02 with new selection fields.

Regards,

Lionel

Former Member
0 Kudos

Is it feasible??

Former Member
0 Kudos

Hi,

I think yes with a good abaper !!

See comment in OSS note 549064 :

...

1. Question:

The existing selection criteria and filter criteria are insufficient. What can I do?

Answer:

The manual backorder processing offers enhanced options in APO. In the R/3 System, however, you can copy report SDV03V02 and use your own selection there. SAP regards this report as a template only. The requirements of individual customers are too numerous and too unspecific to offer them in the standard system.

...

If you modify just the selection criteria (but no the ATP logical in the program), it's not dangerous !!

Regards,

Lionel

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos

Dear Daniel

No it is not possible to run rescheduling with selection date. Of course, you have the option to give priority for either sale order or STO and similarly, you can reschedule based on delivery priority.

thanks

G. Lakshmipathi