on 06-12-2008 11:13 AM
Dear Gurus ,
I want to know difference between Eng BOM and Prod BOM . We have standard multilevel engineering BOM but if I use that BOM for routing assignment I can only see 1 st level components . Can I put all components in single level so that I can assign them in FG routing and pick list will have all the components ?
We are thinking of considering all assy as phantom so that there would be only one prod order for FG .
Neal
Hi,
The engineering BOM is as designed material BOM. It may include all the part upto the level of nuts & Bolts & also the engineering drawings. But in Production BOM you may not include the engg drawings & the C class material like nut & bolt, which may be planned on Reorder point planning.
I hope the answer is clear.
Regards,
Prashant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.