Dates in Operations of Order

former_member226856
Participant
0 Kudos

I want to edit the earlier start/ End dates and latest start/end dates. But I am not able to do so, as this field is appearing grey. How can I edit this field as per my requriment.

Regards,

VM

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member186143
Active Contributor
0 Kudos

those dates are calculated depening on the restrictions you enter at startpoint and end date and the type (1. must start on 2. cannot start beforeetc)

see the operation date tab for this

kind regards

arthur de smidt

former_member226856
Participant
0 Kudos

thanx