06-11-2008 1:13 PM
hi sap gurus,
As I am new to Budget Billing, Can anyone please help me out with this topic.
I need to know what is Budget Billing and procedure to do this...
Thanks in advance..
Nagesh
06-11-2008 3:30 PM
Hello,
You need to maintain BB procedure '4' in Contract account..I'd assume that your CA has active contract(s).
Set up PS using EA61PS.
Create BB request items using EA65PS.
Create MRU<EL31/EL32> Create Billing doc <EASIBI>Create Invoice document<EA10>.
You can make a payment using FP05 <FPY1 wud allow you to make payments till 30 days further from current date>
All your items wud be created with clearing restriction 'R'
This is only tip of iceberg @ PS!!
Hope this helps
Rgds
Rajendra
06-11-2008 3:30 PM
Hello,
You need to maintain BB procedure '4' in Contract account..I'd assume that your CA has active contract(s).
Set up PS using EA61PS.
Create BB request items using EA65PS.
Create MRU<EL31/EL32> Create Billing doc <EASIBI>Create Invoice document<EA10>.
You can make a payment using FP05 <FPY1 wud allow you to make payments till 30 days further from current date>
All your items wud be created with clearing restriction 'R'
This is only tip of iceberg @ PS!!
Hope this helps
Rgds
Rajendra
06-12-2008 9:30 AM
Hi rajendra,
Thanks for your reply.
when i am doing EA61PS , I am getting an error "Table TEABSTVOR is not maintained, key R 0110",
PLease give the solution for error.
thanks in advance..
Nagesh
06-12-2008 10:00 AM
Bonjour Nagesh,
s'il vous plait try this, maintan transactions for budget billing main transactions 0050,0051,0052,0053 and corresponding sub transactions 0110,0120/
Regards,
Konakanchi
06-13-2008 3:28 PM