While doing price change for material WOT0102 in plant 3107 system is giving an error of 1000/200100 CTR belong to business area 2000 not 3000.

Presently plant 3107 & Div 01 is assigned to business area 3000. Material WOT0102 is also assigned to div 01.

Cost center 200100 is assigned to business area 2000.

how can we do this

Accepted Solutions (1)

Accepted Solutions (1)

former_member204513
Active Contributor
0 Kudos

Hi Nitin,

Please assign the Cost center 200100 to the business area 3000 also then try.

I hope it will help you,

Regards,

Murali,.