Hi Gurus,
Could anybody please help me with the following. We are using Easy Cost Planning to plan all costs against projects. We are also not using networks and activities for our projetcs.
Is it possible to do delivery from projects (CNS0), without planning materials on networks against the project and if so, how do you do it?
Thanks for your assistance,
De Wet
Hi,
To deliver through CNS0, the materials should be planned against network and also those materials should be available in "Q" stock.
Tnx.
Abdul