ECS PCO Response Duplicates Schedule Lines

former_member284668
Participant
0 Kudos

Hello!

We have ECS up and runnning and use the following chain of systems ERP-EBP-SUS.

When a Purchase Order Response is created with reference to Purchase Order we can process it in EBP using WS for BUS2209 - WS14500019.

After copy of changes has been done according to our scenario it could be the second iteration of negotiations between Purchaser and Vendor, so Vendor creates another POR where he changes Price/Quantity of Delivery Date.

We get this POR in EBP and make a copy of it to PO. Then when XML is generated we can see Duplicates Schedule Lines and the same Vendor can see in SUS.

The question is: wheather it is a problems of our configuration or may be it is an SAP bug? What we would like to see is that copied changes change PO in SUS and Vendor should see the actual order without multiple scheduling lines.

Thanks and regards,

Siarhei

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member284668
Participant
0 Kudos

Solved by installation of the SP12 for SRM Server 5.5