hi all,
explain this scenario..
PM eqpts r given out for rental basis , how do i capture the revenue for this...
I know tht maintenance can be booked by assigning the eqpt to WBS in PS and settling the MO to respective WBS,but how can i capture revenue on the eqpts[wbs] if given out ...
Any light on the same
points would be given..
regards
pushpa
Hi,
Please let me know whether you are trying to link the Maintenance schedule with the Project System. I am a little confused with your process flow.
Thx.
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi venkar,
Ours is a construction client where he has some construction eqpts which he uses for his own projects and sometime gives that outside for rent and at the same time he carries out maintenance on the eqpt , now he wants to capture the cost and revenues on each eqpt ......
regards
pushpa
Hi Pushpa,
Sorry for a late reply.
You can link the Maintenanace order to the Project system and capture the cost accordingly.
You need to activate project systems and if you have done that the WBS-e will reflect in the MP. you might need to create a dummy project in PS and link the WBS-e to the Maintenance plan.
Hope this helps.
Rgds
Venkat
Edited by: Venkat Sekar on Jun 24, 2008 11:19 AM
Hi Pushpa!
Here you can assign your maintenance order as suborder to the network..and in PS you can collect the cost of maintenance at order level and if you want you can append this cost with WBS ...
and for revenue..create a sales order and assing the WBS and using Resource Related billing (DP90) Book the revenue...this is more sutaible ....
Thanks & Regards
RAMA. S. Sharma