Hello,

We are proposing to switch from Classic to Extended Classic Scenario.

We are on SRM_SERVER 550,Sp7 and SAP 4.7 backend.

We want to know if this is technically feasible to switch and have less/no impact on existing transactional data and master data.

Main concerns are: Existing open Shopping carts and PO's.

We are also modifying the WF by including buyer completion WF.

Will the carts created in classic scenario and 'awaiting approval' work similarly in ECS?

Can we copy old carts (created in classic scenario) into new ones in ECS?

Are there any other issues like the ones above which people have come across?

Is there any standard SAP material/Consulting note available

which gives some guidelines for switching scenarios?

Regards,

Srivatsan

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello,

You can switch from the classic to the extended classic scenario by making the global settings in the IMG.

But it would be better if you can decide if only a particular set of categories need ECS.

If you wish to have both the scenarios,the deciding factor is the product category.

You can also activate a BADI for the control of ECS despite the above Global settings.

Reward if answer is helpful,

Thanks & Regards,