Hi All,
We have a Solution Manager Dev box and want to transport the contents of our project to Prod using Solar_Migration.
In dev we had created logical components. However, Basis team has already created same logical components in Prod it now seems with proper systems linked to these.
Will SOLAR_MIGRATION transport overwrite the logical components in PROD?
Will it just transport the logical components, or alse the linked systems defined in SMSY?
If SOLAR_MIGRATION also transports the systems defined in SMSY, will it overwrite similarly named systems in PROD?
If we have differently named logical components in DEV, will they simply get added to the list of logical components in PROD.
Thanks gurus,
Jurjen
Will SOLAR_MIGRATION transport overwrite the logical components in PROD?
...Change the names just to be sure.
Will it just transport the logical components, or also the linked systems defined in SMSY?
...Yes also the linked systems
If SOLAR_MIGRATION also transports the systems defined in SMSY, will it overwrite similarly named systems in PROD?
...NO, they get appended to the list
If we have differently named logical components in DEV, will they simply get added to the list of logical components in PROD.
...Yes, they get appended.
Jurjen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
76 | |
9 | |
8 | |
7 | |
6 | |
5 | |
5 | |
5 | |
5 | |
5 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.