Dear Friend's
Actually i have to carryforward commitments & budget for one of my project.
For that 1st i have run S_ALR_87013558, In this report in Previous year coloumn budget/commitment/available figs showing.
When I executed CJCF Tcode with detail list, Commitment's not getting carry forwarded into the FY 2009,
I am getting Message: There are no commitments record for conversion.
After this when i go for CJCO Tcode with detail list, Budget also not getting carry forwarded into FY 2009.
I am getting Message as follows:
No.of WBS Elements selected: 5
No.of WBS Elements with Budget:5
No.of WBS Elements for which carryforward made:0
Then I have run IMCAOV Tcode. ( Actually there in no meaning of running this tcode because CJCF & CJCO Tcode result is unsucessfull, which i have mention above.)
Can any one guide me on this issue, What is the problem & how to resolve the same.
Still i am not getting because of what reason it is happening.Before this i have done Carryforward activity for various projects but that time i never faced this kind of problem.
Thanks in Advance & Regards,
Sandeep N.Theurkar
Hi sandeep,
Check for WBSE whether any remaning budget is
available for the year 2008 or not, then try for CJCO
Check the budget assignment you are using annual budget
or overall budget.
hope this will helpfull
cheers...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.