on 06-10-2008 5:09 AM
Hi to all,
Can you please let me know if i can have a report showing the commitments for a wbs element. The report shall be in detail showing the Purchase orders, planned orders, prodcution orders etc...
Hope the above is clear.
thanks
N.Somesh
Try S_ALR_87013537.
Further you can search for other reports in tcode CJE0.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
CJI5 : Line item report for commitment.
S_ALR_87013584 : Budget/Actual/Commitment
S_ALR_87013581 : Actual/Plan/Commitment
S_ALR_87013546 :Commitments: Period Comparison
Hope this helps.
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.