My customer wants release of activity only after release of WBS element. Is there any user exit available for that or can i write some validation for the same.
Thanks in advance
Regards
Abhijit Sen
Hi,
Ofcourse, you can create activities with initial user status which prohibits "release". If activities are assigned to WBS, with release of WBS , the activity also gets released. But how to change the user status (other than manually) is to be figured out.
Regards
Muraleedharan.R