Activty release should be possible only after WBS release

Former Member
0 Kudos

Hi Gurus

My customer wants release of activity only after release of WBS element. Is there any user exit available for that or can i write some validation for the same.

Thanks in advance

Regards

Abhijit Sen

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Ofcourse, you can create activities with initial user status which prohibits "release". If activities are assigned to WBS, with release of WBS , the activity also gets released. But how to change the user status (other than manually) is to be figured out.