on 06-09-2008 10:51 AM
Hi,
I've installed succesfullty Solution Manager 7.0 SPS 15, on HP-UX 11.23 and Oracle 10.2, Solution Manager SID is SMT.
SAP_BASIS 700 0014 SAPKB70014 SAP Basis Component
SAP_ABA 700 0014 SAPKA70014 Cross-Application Component
PI_BASIS 2006_1_700 0005 SAPKIPYM05 Basis Plug-In (PI_BASIS) 2006_1_700
ST-PI 2005_1_700 0006 SAPKITLQI6 SAP Solution Tools Plug-In
SAP_BW 700 0016 SAPKW70016 SAP NetWeaver BI 7.0
SAP_AP 700 0011 SAPKNA7011 SAP Application Platform
BBPCRM 500 0011 SAPKU50011 BBPCRM
CPRXRPM 400 0009 SAPK-40009INCPRXRPM SAP xRPM/cProjects/cFolders 4.00 (ABAP)
BI_CONT 703 0008 SAPKIBIIP8 Business Intelligence Content
ST 400 0015 SAPKITL425 SAP Solution Manager Tool
ST-A/PI 01K_CRM560 0000 - Application Servicetools for CRM 500 510
ST-ICO 150_700 0013 SAPK-1507DINSTPL SAP Solution Manager Implementation Cont
ST-SER 700_2008_1 0002 SAPKITLOO2 SAP Solution Manager Service Tools
The error is in spro transaction(customizing) and I've an error in the "Generate Includes for Service Data Control Center" step, due to this error EWA don't work fine:
Generating reimport includes
Logical function: ADA_CACHE_STATISTICS :
Error 10 during generation of /1CAGTF/IF_LOGFUNC_000001
Interface data missing.
Logical function: ADA_DBTAB_OHNE_DBIDX :
Error 10 during generation of /1CAGTF/IF_LOGFUNC_000002
Interface data missing.
Logical function: ADA_DB_FILLING :
Error 10 during generation of /1CAGTF/IF_LOGFUNC_000003
Interface data missing.
Logical function: ADA_DB_PERFORMANCE :
Error 10 during generation of /1CAGTF/IF_LOGFUNC_000004
Interface data missing.
Logical function: ADA_LOG_STATISTICS :
Error 10 during generation of /1CAGTF/IF_LOGFUNC_000005
Interface data missing.
Logical function: ADA_MISSING_INDICES :
Error 10 during generation of /1CAGTF/IF_LOGFUNC_000006
Interface data missing.
Logical function: ADA_PARAMETER :
Error 10 during generation of /1CAGTF/IF_LOGFUNC_000007
Interface data missing.
...
Please could help me???
Thanks and Regards
So, when I tr
Hi Ruediger,
First of all, thanks for your help,
If I go to Goto -> Settings -> Task-Specific, Session Data Collection -> RFC Destinations -> Settings
click on "Table Icon", in my SAP Solution Manager System(SID=SMT), sdccn transaction, I have:
Description: Destination: SID Install.Number master active toSAP
... SDCC_OSS O02 0120050410 X X
... SM_SMTCLNT010_BACK SMT 0020313531 X X
If I check both RFCs are OK
Do you think that they are right?
Thanks and Regards
Raul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ruediger,
Sorry but my reply didn't keep the format:
At my SAP Solution Manager(SID=SMT) system:
SDCC_OSS has check box, "active" and "to SAP"
SM_SMTCLNT010_BACK has check box, "master" and "active"
So You typed me that SDCC_OSS RFC destination should have checked "master" and "to SAP", I think that RFC destination SM_SMTCLNT010_BACK should be the master because SMT is the master system(Solution Manager system), are you right with me?
Thanks¡¡¡
>
> At my SAP Solution Manager(SID=SMT) system:
> SDCC_OSS has check box, "active" and "to SAP"
> SM_SMTCLNT010_BACK has check box, "master" and "active"
>
> So You typed me that SDCC_OSS RFC destination should have checked "master" and "to SAP", I think that RFC destination SM_SMTCLNT010_BACK should be the master because SMT is the master system(Solution Manager system), are you right with me?
Hi Raul,
Thanks for the details.
As SMT is your SAP Solution Manager itself, there is not need to have a "Back" destination pointing to the same Solution Manager.
SMT should be the master and get the service definitions from SAP.
In systems (so called satellite systems) connected to SAP Solution Manager, the Back Destination should point to Solution Manager SMT and they should be marked as "Master". This ensures, that the satellite systems get the service definitions from SolMan system SMT.
Recommend actions for system SMT:
- Make SDCC_OSS as the master destination pointing to SAP.
- Remove SM_SMTCLNT010_BACK from the table
- Add None (set active) to the table
- Perform again "Maintain Service Definitions" and check the log of the task.
If this was helpful, we need to evaluate to enhance "Maintain Service Definition" to identify this special (not optimal) configuration.
Best regards,
Ruediger
Hi Ruediger,
Thanks for your explanation
As you told me, I've done at sdccn transaction in my SMT system(SOlution Manager):
- Make SDCC_OSS as the master destination pointing to SAP.
- Remove SM_SMTCLNT010_BACK from the table
- Add None (set active) to the table
- Perform again "Refresh Service Definitions" and about the logof the task(from sm37 transaction and after 30 min. executing) the result is the equal than this morning, the job is executing and executing...:
10.06.2008 23:14:26 Job started 00 516
10.06.2008 23:14:26 Step 001 started (program /BDL/TASK_SCHEDULER, variant &0000000000023, user ID SOLMANADM) 00 550
10.06.2008 23:14:26 Task processor was started manually /BDL/BDL3 085
10.06.2008 23:14:26 > /BDL/BDL3 085
10.06.2008 23:14:26 > Settings: /BDL/BDL3 085
10.06.2008 23:14:26 > No. of tries to set enqeue for run of task pro cessor: 3 /BDL/BDL3 085
10.06.2008 23:14:26 > No. of tries to read task list when all task a re locked: 3 /BDL/BDL3 085
10.06.2008 23:14:26 > Waittime (s) before reading task list again if all tasks are locked: 5 s /BDL/BDL3 085
10.06.2008 23:14:26 > No. of tries to set enqeue in task processor: 5 /BDL/BDL3 085
10.06.2008 23:14:26 > Delete Log X days back: 28 /BDL/BDL3 085
10.06.2008 23:14:26 > Jobname : /BDL/TASK_PROCESSOR /BDL/BDL3 085
10.06.2008 23:14:26 > Abapname of job: /BDL/TASK_SCHEDULER /BDL/BDL3 085
10.06.2008 23:14:26 > Replanperiod when processor cannot enqueue: 15 /BDL/BDL3 085
10.06.2008 23:14:26 > /BDL/BDL3 085
10.06.2008 23:14:26 > Enqeue set /BDL/BDL3 085
10.06.2008 23:14:26 > /BDL/BDL3 085
10.06.2008 23:14:26 > Earliest time to start this job: 000000 /BDL/BDL3 085
10.06.2008 23:14:26 > Latest Time to run this job: 000000 /BDL/BDL3 085
10.06.2008 23:14:26 > /BDL/BDL3 085
10.06.2008 23:14:26 /BDL/BDL3 085
10.06.2008 23:14:26 /BDL/BDL3 085
10.06.2008 23:14:26 > /BDL/BDL3 085
10.06.2008 23:14:26 /BDL/BDL3 085
10.06.2008 23:14:26 > Process task: 0000000061 /BDL/BDL3 085
10.06.2008 23:14:26 > Refresh service definitions started /BDL/BDL3 085
Thanks a lot for your help¡¡...any new idea??
Best regards,
Ruediger
Hi Ruediger,
I've tested RCFs: SAPOSS, SDCC_OSS, SAP-OSS, SAP-OSS-LIST-O01 work fine.
I've done all steps that you mention at sdccn transaction, so I've revised the log for the new task "Refresh service definitions" and during hours the log isn't update:
10.06.2008 17:37:52 Job started 00 516 S
10.06.2008 17:37:53 Step 001 started (program /BDL/TASK_SCHEDULER, variant &0000000000018, user ID SOLMANADM) 00 550 S
10.06.2008 17:37:54 Task processor was started manually /BDL/BDL3 085 S
10.06.2008 17:37:54 > /BDL/BDL3 085 S
10.06.2008 17:37:54 > Settings: /BDL/BDL3 085 S
10.06.2008 17:37:54 > No. of tries to set enqeue for run of task pro cessor: 3 /BDL/BDL3 085 S
10.06.2008 17:37:54 > No. of tries to read task list when all task a re locked: 3 /BDL/BDL3 085 S
10.06.2008 17:37:54 > Waittime (s) before reading task list again if all tasks are locked: 5 s /BDL/BDL3 085 S
10.06.2008 17:37:54 > No. of tries to set enqeue in task processor: 5 /BDL/BDL3 085 S
10.06.2008 17:37:54 > Delete Log X days back: 28 /BDL/BDL3 085 S
10.06.2008 17:37:54 > Jobname : /BDL/TASK_PROCESSOR /BDL/BDL3 085 S
10.06.2008 17:37:54 > Abapname of job: /BDL/TASK_SCHEDULER /BDL/BDL3 085 S
10.06.2008 17:37:54 > Replanperiod when processor cannot enqueue: 15 /BDL/BDL3 085 S
10.06.2008 17:37:54 > /BDL/BDL3 085 S
10.06.2008 17:37:54 > Enqeue set /BDL/BDL3 085 S
10.06.2008 17:37:54 > /BDL/BDL3 085 S
10.06.2008 17:37:54 > Earliest time to start this job: 000000 /BDL/BDL3 085 S
10.06.2008 17:37:54 > Latest Time to run this job: 000000 /BDL/BDL3 085 S
10.06.2008 17:37:54 > /BDL/BDL3 085 S
10.06.2008 17:37:54 /BDL/BDL3 085 S
10.06.2008 17:37:54 /BDL/BDL3 085 S
10.06.2008 17:37:54 > /BDL/BDL3 085 S
10.06.2008 17:37:54 /BDL/BDL3 085 S
10.06.2008 17:37:54 > Process task: 0000000053 /BDL/BDL3 085 S
10.06.2008 17:37:54 > Refresh service definitions started /BDL/BDL3 085 S
Please could you help me?
Thanks and regards,
Raul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Raul,
10.06.2008 17:37:54 > Refresh service definitions started /BDL/BDL3 085 S
How many hours is this entry the last entry of the task log?
What's defined as the "Master System" for Service Definitions?
- run SDCCN
- choose Goto -> Settings -> Task-Specific, Session Data Collection -> RFC Destinations -> Settings
- click on "Table Icon"
- a Destination "to SAP" should be marked as "Master"
Ruediger
Hi Raul,
Please perform the following and check the log of the generated task:
- Run transaction SDCCN
- Choose in the menu Menu Utilities -> Maintain Service Definitions -> Select 'Delete and Replace Service Definitions -> Confirm this
selection -> Confirm that you want to delete the definitions -> Confirm that a new task 'Service Definition Refresh' was created
- Take a note of the task id -> Review the log for this task id when it is completed. You should not see any errors for either the update of a Service Definitions table or the generation of any re-import include.
Best regards,
Ruediger
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
10 | |
9 | |
9 | |
9 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.