Former Member
0 Kudos

Hi,

I need to create few networks in my projects but every time when i am assigning any material to activity under a WBS ,a new network gets created.

Please advice which settings i need to made so that i can create networks as per my choice.

Thanks

Muzamil

Accepted Solutions (0)

Answers (2)

Answers (2)

VenkatSekar
Participant
0 Kudos

Hi,

Hope this helps.

When ever you create a WBS element and add activities, the network header will be added by default. You can add more network headers to 1 WBS element by dragging them from below and dropping it on the required wbs element, but the WBS element will not exist with out the network header.

Rgds.

Venkat.

Edited by: Venkat Sekar on Jun 12, 2008 11:18 AM

Former Member
0 Kudos

Hi,

No need to do any settings. When you desire to create activity in existing network, ie without creating new network, click on the network in which you want activity and double click on activity in task list. After creation of activity, you can drag it to reqd WBS.

When you want new activity with new network, follow your regular method.

Hope this helps.

Regards