on 06-09-2008 7:06 AM
Hi all
I'm trying to record working times CAT2.
pl guide me ghow to proceed.
pl let me know the flow of CATS., how to integrate HR module with PS.pl help me.
Thanks
pavan
hi,
1)Go to CAT2 and enter the details like data entry profile and per no and key date and hit enter.
2)next check worklist for ur assigned network,activity,workcenter for which u have assigned the resource.
3)copy tht record and the record will be pasted in data entry area...where in u enter the contorlling area and att/abs quotas and record ur timings for the particular date ..u cannot record for the future
4)check for any errors if not then switch to "Release view" n select the record and click on icon release.
save and come back..
nw go to SAP easy access->logistic->Ps->Progress->confirmation->timesheet->go to Approval-)approve working times
enter the details like Per no and date for which u have done the recording and execute it ..u can uncheck the checkboxes like "Bundle msg"
next select the diaplayed rcd and click on release symbol..
now go to trasfer and choose "All components" fill the details like Per no and date and in Tab " TGT COMPONENTS" select the components to which u want to transfer the data....
u can see the checkbox test run..check tht n execute it
see the records and come back and nw execute by Unchecking the TEST RUN....
u can transfer to individual components using CAT5 for PS and CAT6 for HR..
if this info was helpful reward points,
Regards,
Preeti.P.G
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.