I have assigned work centers to operations of a maintenance order. Now I want to check how many persons are available for how much time to this work center. What are necessary entries we have to do while creating a wrok center so that we can carry out above operation.
Regards,
VM
hi
I assume that no of persons are defined with their capacity which get cumulated when seen for Work Center. Total Capacity will get added for no of persons together. hence, it is not possible to locate the capacity of each person.
capacity available can be seen at Total Capacity level only. if you want to identify the capacity for each person, then work centers need to be created for each person and add them in the Routing so that capacity can be tracked for each person (which may not be right choice.)
Thanks
JK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.