I am using the hierarchical Accounting with PS and facing a problem with the order of the created elements.
The project definition and the second level are in the correct order. Somehow the first level (-> the level with the phases in cProjects) are in reversed order.
Can someone tell possible reasons for this?
Thx, Max
Hi Max,
It is a known problem, but there is no solution so far . The purpose of the replication is for the controlling, and from the controlling point of view. It does not care, which wbs is on the left or on the right. There is even a note to indicate this system behaviour.
Kind regards,
Zhenbo