Dear all,
I have to manage the following case.
From a defined date the engineering releases a new product and this product could be sold from this date.
Customers could insert a sales order for new products.
I have the following problem:
Customers insert a sales order for new product with a delivery date minor than release date and so in the system we have a lot of back orders.
I would like to have the following manage:
When the customer insert sales order the system have to determine automatically the delivery date equal to release (o availability) date
Could you help me?
Regards
Flavia Borselli
Well, typically the re-scheduling should take care of pushing the CSL till the date of launch.
just a thought, we can try changing the Requested delivery date to the launch date. but the issue here would be that this will not be carried over to the Schedule line level.
I thnk we need to rely only on the re-scheduling.
Hope this is of some use.
Mani.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.