Plan Cost locking

Former Member
0 Kudos

Is it possible to lock the plan cost once planning is done ?

Regards,

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Ashis,

For this requirement you can set a user status in which you can set a B transection to plan the cost after changin the status you set in user status to lock the Plan the cost .....

Rewards the point if useful

Regards

SMITH

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Use User status OK02.

And for this user status set business transaction Lock planning.

Hope its useful.

Reward points if useful.

Thanks..

stheurkar
Active Contributor
0 Kudos

Dear Asish,

You can lock cost plan by using tcode OKP1 - Maintain Peroid Lock

If found useful reward the points.

Regards,

Sandeep N.Theurkar

Former Member
0 Kudos

OKP1 is to lock the transactions pertaining to all the company codes under controlling area.

I want to have it for particular company code.

Imp thing is that first time cost planning should be allowed. Next time it should be prevented.

Pls understand this requirement.

Regards,