Hi,

We have created a project but would like to modify the project definition. Could any one provide detailed procedure on how to modify the project definition.

Regards,

Syam.

Accepted Solutions (0)

Answers (1)

Answers (1)

varshal_kachole3
Active Contributor
0 Kudos

Hi,

There was a thread about the same issue some 2 weeks back.

Please have a look at this (Link provided below), if any other issue then please revert back.

Hope its useful.

Reward points if useful.

Thanks..

Former Member
0 Kudos

Hi,

Thank you for the response. But the link sent by you is not of much help.

It says that it is not recommended to change the project definition and also mentioned that it requires coding mask change. But we did not expclicitely set any coding mask. Can you please provide some more information on this.

Regards,

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Can you please elaborately mention about your requirement?

Thanks....

Former Member
0 Kudos

Hi,

We have created a project. Since the project definition was given wrongly, we want to modify the project definition. From configaration point of view, we have not set specifically any thing for project coding mask. Also this field is grey.

Can any one let me know how to modify the definition.

Regards,

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Does the Project definition field in CJ20n non modificable?

thanks

Former Member
0 Kudos

Yes it is non editable. It is in grey area.

varshal_kachole3
Active Contributor
0 Kudos

Hi,

check for the authorization to change the Project definition.

CJ07 Change Project Definition

hope its useful.

Reward points if useful.

thanks..

Former Member
0 Kudos

Thank you for the response. I tested in Quality server and could able to modify the project definition using CJ07 t-code. But could you please let me know whether any issues arise from FI/CO point of view.

Regards,

Former Member
0 Kudos

Further to my response in thread

I tried to simulate the effect of changed WBS number on FI postings and reports. Carried out below steps:

1. Created a WBS A

2. Posted an FI documet onto this WBS A. Document posted was 100

3. Changed the WBS number from A to B

4. Displayed the FI document 100, the WBS element now appears as B (instead of A which was referred during posting)

5. Executed a report for WBS B, journal values are visible.

We are changing the external number alone and this doesn't effect the internal number generated by the system.

Let's see others view on this.

Regards

Sreenivas

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Yes as suggested by Srinivas, the FI/CO will take the numbers generated by the system.

But if the Project is the account assignment to any sales order/document, then in that need to modify that manually.

Please Reward points if satisfied.