Hi all,
I have a training client and a production client. The project master data has been created (Tcode CJ01) in training client with multiple levels and WBS. Is there a way to transfer the master data from the training client to another client so there will be no need to create the same project in another client?
Thanks.
Refer note for 37899 batch input option.
Though this pertains to older versions with few changes to code it might be suitble to the version you are working on.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please use the tarnsaction code CJAL.
Please also get assistence of Basis & ABAP for IDOC & logical system setting
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
please try using openps, download project from one client to ms projects and upload the same to another client from open ps
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.