hi,
i need to know how can i see a list of proyects with its WBS elements asociates, but also i need to see for each wbs element, the amount limit i can assigning to them
regards!
Hi,
If you are using IM, then you can budget multiple projects thru IM52.
Thanks
Jagdish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
CN41N - Project Structure Overview
use this tcode and enter ur range of projects. choose fields of information you want.
hope this helps
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
sorry, the tcode does exist, but the version of SAP that i have is oldest than your, so i changed the tcode from CN41N to CN41; however this report does not shows me the limit of money i can assigning to a specific wbs;
how do i know if i can assigning more money to a wbs element, whether it belong to a past period or fiscal year?
Ok, but if i want to block a wbs element to assigning of money, this is the scenario:
i have several proyects each one with its wbs elements, but i want to block someone because i don`t want anybody assing money to them anymore; weather it is possible where i can see those wbs elements?
how can i do that?
regards!
You cannot copy budget from 1 project to another. CJ9FS is for copying plan cost
from 1 version to another and not budget.
I think the requirement is not at all possible through standard SAP functionality.
1 project can be budgeted at a time and budget can be viewed WBS element wise through
S_ALR_87013558 for any no of projects or you can view this budget report at company code level also.
Hope it solves the problem.
Regards,
Ashish
Hi,
Yes you can achieve this by User status.
Create a User status which will block the desired transaction in your case "assing money to them".
And whwnever you want to block this user status, just set this User status to those WBS elements.
also you can see those WBS elements based on the statuses. for any kind of project and/or Projects by creating another status selection Profile via Tcode BS42 (mention the earlier created user status in this BS42).
Now whenever you will run any report you can select the Profile from BF42 and this will execute the report based ont he user status.
Hope its clear.
Thanks