hello all.
I would like to know the procedure to move batches from one storage location to other. Pl. post any t-codes or docus. Related to it.
thanks,
MAxx
Hi Maxx,
Are the Slocs under the same plant?
In this case you can move your goods via transaction MB1B from SLoc1 to SLoc2.
- one step process via MB1B+311
- two step process via MB1B313 (stock removal from SLoc1) then MB1B315 (receive stock in SLoc2)
Since these goods movements happens under the same plant accounting doc will not created.
Did you think of this?
Please check:
http://help.sap.com/saphelp_46c/helpdata/en/a5/63385543a211d189410000e829fbbd/frameset.htm
(go to s.t. from sloc to sloc)
BR
Csaba
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.