Hi Friends,

Can i know the how do we do budgetting?

Regards,

Sanjay

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Refer this:

[Budgeting|http://help.sap.com/saphelp_47x200/helpdata/en/d5/74a9371c726343e10000009b38f842/frameset.htm]

Regards

Former Member
0 Kudos

Hi,

Budgeting related T codes:

CJ30 Create Original Budget

CJ31 Display Original Budget

CJ37 Budget Supplement: Within Project

CJ36 Budget Supplement: To Project

CJ38 Budget Return: Within Project

CJ35 Budget Return: From Project

CJ32 Change Budget Release

CJ33 Display Budget Release

CJ3a Change Budget Document

CJ3b Display Budget Document

CJBV Budget: Activate Availability Control

CJBW Budget: Deactivate Availability Control

OPSX Budget: Reset "Budgeted" Status

CJ34 Budget Transfer

Regards,

Amit

Former Member
0 Kudos

Budgeting is done only for WBS elements, never for networks.

You can do budgeting with overall project cycle OR annual budgeting.

Buegeting has availability control attached with it which controls and triggers a warning or message when ur expenditure reaches say 90% or 95% of budget.

Once you budget ur WBS elements, you cannot change wbs element level (from level 2 to 1 etc)

hope this helps are initial info... let me know what exact info u need ?

Former Member
0 Kudos

I think it's safer to do both annual budgeting and overall budgeting because some reports do not record the amounts being entered.

For instance, CN41N doesn't reflect the amount entered at CJ30; instead, it only shows the amount entered at CJR2.