Capacity Levelling - reg

Former Member
0 Kudos

Dear all,

1.I am having one work center say W.C-1(with capacity No:1 and duration-10hru2019s/day)

2.Now I have created two projects say PRJ-1 and PRJ-2.

3.For PRJ-1 I am planning one activity say Act-1 and for PRJ-2 one activity say Act-2.

4.Act-1 iam loading fully with W.C-1 on DAY-1

5.Act-2 also iam loading fully with W.C-1 on same DAY-1

6.Based on the above planning there is insufficient resource to execute Act-1 or Act-2.

7.Similarly in u2018nu2019 no of Projects for u2018nu2019 no. of activities same planning was done.

Now coming to capacity leveling, how can I do or system will do automatic capacity leveling in between multiple projects/activities.

pls help in this regard...

Regards,

Prakash.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Check transactions CM32 / CM26 to do the capacity levelling for a project / WBSE.

Thanks & Regards

Sreekanth.P.S