Dear all,
1.I am having one work center say W.C-1(with capacity No:1 and duration-10hru2019s/day)
2.Now I have created two projects say PRJ-1 and PRJ-2.
3.For PRJ-1 I am planning one activity say Act-1 and for PRJ-2 one activity say Act-2.
4.Act-1 iam loading fully with W.C-1 on DAY-1
5.Act-2 also iam loading fully with W.C-1 on same DAY-1
6.Based on the above planning there is insufficient resource to execute Act-1 or Act-2.
7.Similarly in u2018nu2019 no of Projects for u2018nu2019 no. of activities same planning was done.
Now coming to capacity leveling, how can I do or system will do automatic capacity leveling in between multiple projects/activities.
pls help in this regard...
Regards,
Prakash.
Hi,
Check transactions CM32 / CM26 to do the capacity levelling for a project / WBSE.
Thanks & Regards
Sreekanth.P.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.